Time Clauses and Modern Courts
Time for performance
Time Clauses and Modern Courts
A closing date can end a land contract or cost the late party nothing more than damages, and the difference often turns on one sentence: time is of the essence. Courts once treated that sentence as decisive. Modern courts treat it as evidence. They ask whether the date mattered to these two parties, and they weigh the sentence with everything else the record shows about the deal.
The shift changes what a careful party does at closing. A seller who cancels over a missed date on the strength of boilerplate alone may find that the court sees a minor delay and that the seller, not the buyer, is the party in breach. A drafter who wants the date to hold must give the court reasons beyond the sentence. The first subsection compares the traditional and modern views, and the second shows how to draft a deadline that survives them.
Traditional Versus Modern View
A time-is-of-the-essence clause is a contractual provision making timely performance a condition.1 The traditional view took that definition at face value. Tender of strict performance on time was treated as a condition, and failure of the condition was a total breach that fully discharged the other party. The late party could therefore not enforce the contract in law or in equity unless the other side waived timely performance. Some courts applied the rule with exceptional rigidity: in Doctorman v. Schroeder, the New Jersey Court of Errors and Appeals refused specific performance to buyers who were only thirty minutes late. Others were somewhat more lenient when the late party was a purchaser who stood to forfeit a large earnest money deposit, but significant tardiness still cost the right to enforce.2
The modern trend loosens that grip. Comment d to Restatement (Second) § 242 suggests that stock phrases such as “time is of the essence” do not necessarily make every delay material, and that such phrases are to be considered “along with other circumstances.”3 The reason lies in where the phrase comes from. It has become standard language in many contracts, even where nothing shows that exact timing matters to the parties, and some courts have treated it as an obligation subject to substantial performance even though it is an express condition.4 A sentence found in so many forms says little about what these two parties wanted. On this view the clause is just one factor in deciding whether a breach is material, and a court must consider all the circumstances before deciding that it is.5
Those circumstances are the ones Restatement (Second) § 241 lists. A court asks how far the injured party will be deprived of the benefit it reasonably expected;6 how far that party can be adequately compensated for the part of the benefit it will lose;7 how much forfeiture the late party will suffer;8 how likely the late party is to cure, taking account of all the circumstances including any reasonable assurances;9 and how far the late party's behavior comports with good faith and fair dealing.10 An essence clause is not on that list. The court considers the clause along with these circumstances, and the clause does not replace them.
Two decisions show the trend at work. In Foundation Development Corp. v. Loehmann's, a commercial lease contained a time-is-of-the-essence clause, yet the clause did not entitle the landlord to terminate when the tenant paid a common area charge two days late; the delay was both inadvertent and trivial. In ADC Orange, Inc. v. Coyote Acres, Inc., a land sale contract required the buyer to make an interim payment of $250,000 “in no event later than December 31, 2001.” That wording was not enough to make time of the essence, so a payment made two weeks late was not a material breach and the contract was not discharged.11 The two cases ask different questions. Loehmann's asks what an essence clause is worth when nothing else shows that timing mattered, and ADC Orange asks whether firm deadline wording short of that clause can make time essential at all. Both answers favored the late party.
A clear condition fares differently. In Elda Arnhold and Byzantio, L.L.C. v. Ocean Atlantic Woodland Corp., the Seventh Circuit enforced a “drop dead” clause in a settlement agreement although the purchaser missed the closing deadline by only one day and would lose $1.7 million if the contract were not enforced. The court applied a two-part test that looked to the parties' intention and to equitable factors.12 A drop-dead date is a date by which performance is required as a condition,13 and the Restatement comment recognizes that the parties may make performance by a stated date a “condition to their agreement,” in which case delay beyond that date, unless the condition is excused, results in discharge.14 The length of the delay and the size of the loss therefore do not separate Loehmann's from Elda Arnhold. What separates them is what the parties agreed and said about the date.
The stage at which the delay occurs also changes its weight. A breach at the outset of performance that affects the value of the entire exchange is likely to be more material than one near the end that affects only a small aspect of what was promised.15 Land sales add a policy reason for patience. Moderate delays are common in real estate sales and rarely so harmful as to justify discharging the aggrieved party. Equity treats time as essential only if the contract or the surrounding circumstances make it so, and it finds no breach until performance becomes unreasonably late.16 A court that already regards modest delay as ordinary in a closing has little reason to treat a stock sentence as proof that this delay was serious.
None of this repeals the strict compliance rule taught earlier in this chapter. The two doctrines work at different steps. The modern view answers whether time is truly essential, that is, whether the contract read with its surrounding circumstances made the date a condition. Strict compliance answers what follows once it did: late tender fails the condition, discharges the other party, and leaves the late party unable to enforce the contract.17 A court that finds an express condition or a drop-dead date applies the strict rule in full. A court that finds only boilerplate treats a short delay as a nonmaterial breach, which gives the aggrieved party damages for the delay and leaves both parties bound.18
The classification carries a risk for the party who insists on the date. If the breach is not material, the aggrieved party must keep performing and may recover damages incurred to that point, but it has no right to suspend or terminate. If the breach is material, that party may either continue and treat the breach as partial or stop and treat it as total.19 A seller who cancels over a short delay on boilerplate alone is therefore betting that a court will find the delay material, and a seller who loses that bet has stopped performing without justification.
Drafting Effective Clauses
The modern approach turns the drafter's job from inserting a sentence into proving a point, namely that timing was material to this deal. Boilerplate invites the opposite inference. Cases are legion in which courts have found that essence clauses are “mere boilerplate,” contradicted by other words in the contract or by the parties' own actions. A determined court can often find some way to excuse a failed condition, and it can usually do so in a ruling so fact-based that it is largely immune on appeal.21 A drafter cannot handcuff such a court but can make it harder to dismiss a five-word boilerplate statement of an important condition.22
The first question belongs to the client, not the form: how important is time? If it is very important, the drafter should include a time-is-of-the-essence clause or word the requirement so that it is both a promise, the breach of which results in damages, and an express condition, the failure of which excuses the client's further performance. If time is important but not critical, the drafter should find out what delay the client will accept as excusable and consider reasonable liquidated damages, an agreed sum payable for lateness, for other delay.23
The first three steps make it clear that the parties agreed time of performance was material to their deal.24 A recital giving the reason, such as a replacement home that must be paid for from the sale proceeds, is specific to these parties and written before any dispute, so it is evidence of the benefit each side reasonably expected, the first circumstance the Restatement lists.25 A covenant placed beside the price makes the date part of what each side promised, which adds damages for breach even where a court hesitates to treat lateness as discharge.
Spelling out notice, cure, and remedy answers questions a court would otherwise settle for itself. Those questions are whether the late party is likely to cure26 and whether money can adequately compensate the other side for the delay.27 A drafter who writes the consequence into the condition, states why the condition is there, and states that it was a fundamental inducement leaves a court less room to excuse its failure.28
The fifth point in the first step matters most in land sales, which commonly set separate dates for the inspection response, the mortgage commitment, title objections, and closing. A single general sentence leaves open which of those performances the parties meant to enforce strictly. Because a condition fails against whichever party is late, the drafter should also confirm that the client can meet every date it asks the other side to treat as essential.29
A well-built clause still depends on what the client does after signing. Courts weigh the parties' actions against boilerplate, so a client who accepts late performance without objection, as the first seller above did, hands the other side evidence that the date never mattered.30 A late party who is not entitled to enforce the contract may regain that entitlement if the other side waives timely performance.31 The drafter should therefore tell the client to respond consistently when a date passes.