Also known as:FRCP 50 · Fed. R. Civ. P. 50 · rule 50 motion · judgment as a matter of law · Rule 50(a) · JMOL
Written by attorneys — see sources below.
A procedural rule permitting a court to enter judgment as a matter of law when a party has been fully heard on an issue during a jury trial and no reasonable jury would have a legally sufficient evidentiary basis to find for that party.
See Our Sources· 7 primary sources
Cases
Federal Rules
How its tested
Common Examples
6
Causation Evidence Challenged Mid-Trial
Elm Eco rested after offering photographs of discolored water near Pinnacle Clean's outfall, resident testimony about odors and respiratory complaints, and a state inspection report. Pinnacle Clean moved for judgment as a matter of law before submission to the jury, arguing the evidence supplied no legally sufficient basis for a reasonable jury to find causation on the nuisance claim. The court took the motion under advisement and submitted the case to the jury.
Timely Motion Specifies Judgment Sought
After Sean rested in his wage misclassification suit against Global Cargo, the company moved before the case went to the jury. The motion expressly requested judgment on the employee-status claim and identified the controlling law plus the facts showing insufficient evidence of control. The court considered the motion on its merits rather than rejecting it for procedural defects.
Summary Judgment Motion Filed Post-Discovery
Ridge Retail moved for summary judgment on Dusk Outlet's breach and negligence claims twenty-five days after the final discovery deadline. The motion identified both claims and asserted that the spreadsheet, affidavit, and complaint logs established no genuine dispute of material fact. The court evaluated whether the movant had shown entitlement to judgment as a matter of law on the record presented.
Defendant Moves Without Resting
Metro Properties moved for judgment as a matter of law at the close of Harper Office Investments' case on the earnest-money claim. The court sustained the motion without allowing Metro to present its own evidence on material breach. On appeal the reviewing court held that the ruling improperly deprived Metro of its opportunity to offer a defense.
Byrd v. Blue Ridge Rural Electrical Cooperative, Inc.356 U.S. 525, 537–38 (1958)
The petitioner, a resident of North Carolina, sued respondent, a South Carolina corporation, for damages for injuries allegedly caused by the respondent's negligence. He was employed as a lineman in the construction crew of a construction contractor.
Respondent Blue Ridge Rural Electrical Cooperative, Inc., a South Carolina corporation in the business of selling electric power, had contracted with R. H. Bouligny, Inc. for $334,300 to build approximately 24 miles of new power lines, reconvert about 88 miles of existing lines to higher capacities, and construct two new substations and a breaker station. The petitioner was injured while connecting power lines to one of the new substations.
Byrd first recovered full benefits under the South Carolina Workmen's Compensation Law from his direct employer Bouligny. He then filed a negligence action against Blue Ridge in the United States District Court for the Western District of South Carolina under diversity jurisdiction pursuant to 28 U.S.C. § 1332.
At trial Blue Ridge asserted an affirmative defense that Byrd qualified as its statutory employee because the contracted work was part of its trade, business, or occupation. Blue Ridge's manager testified on direct examination that three of its substations had been built by its own construction and maintenance crews. His answers on cross-examination created uncertainty that prompted the trial judge to note he appeared to have changed his testimony. Blue Ridge also introduced evidence that it financed the project with a federal loan, purchased the materials, and maintained an engineering service contract with an independent firm for design and supervision. Its charter under the South Carolina Rural Electric Cooperative Act authorized it to construct generating plants, buildings, and equipment necessary for its operations.
After all evidence was presented the district judge struck the affirmative defense, ruling that Blue Ridge could not be a statutory employer because its crews performed work only for its own use rather than for others. The judge then denied Blue Ridge's motion for a directed verdict and submitted the negligence claim to the jury, which returned a verdict for Byrd in the amount of $126,786.80. The Court of Appeals for the Fourth Circuit reversed, resolved uncertainties in the manager's testimony in Blue Ridge's favor, and directed entry of judgment for Blue Ridge without remanding for further proceedings. Byrd petitioned for certiorari, which the Supreme Court granted. The case had previously been dismissed on the ground that Blue Ridge enjoyed tort immunity as a nonprofit corporation, but the Court of Appeals had reversed that dismissal and remanded for trial. On the present appeal the Court of Appeals did not reach other grounds raised by Blue Ridge because its resolution of the statutory employer issue disposed of the case.
Movant Must Show Absence of Genuine Dispute
Celotex moved for summary judgment in the asbestos wrongful-death action, pointing to the absence of evidence that its product caused the decedent's exposure. Catrett responded with no affirmative proof linking the product to the injury. The court granted the motion because the record contained no triable issue on causation.
Celotex Corp. v. Catrett477 U.S. 317, 323 (1986)
In September 1980 respondent Catrett, as administratrix of her husband's estate, commenced a wrongful-death action in the Superior Court of the District of Columbia against fifteen named corporations including petitioner Celotex Corporation.
The complaint alleged that her husband Louis H. Catrett died in 1979 from exposure to asbestos products manufactured or distributed by the defendants. The action was removed to the United States District Court for the District of Columbia on diversity grounds.
After extensive discovery Celotex filed a motion for summary judgment in September 1981 asserting that respondent had failed to produce any evidence that the decedent had been exposed to Celotex asbestos products. In response respondent produced a transcript of the decedent's deposition taken in a separate California proceeding, a letter from an official of one of Celotex's former insurance companies, and a letter from one of Celotex's customers.
In July 1982 the District Court granted summary judgment to Celotex on the ground that respondent had made no showing of exposure to Celotex products in the District of Columbia or elsewhere within the statutory period. Respondent appealed only that ruling.
A divided panel of the Court of Appeals for the District of Columbia Circuit reversed, holding that Celotex had failed to meet its initial burden because it made no effort to adduce affirmative evidence supporting its motion. The Supreme Court granted certiorari to resolve a conflict among the circuits concerning the proper standard under Rule 56.
Jury Instructions Preserve Fact Questions
Del Monte Dunes presented evidence that the city's repeated permit denials lacked a reasonable relationship to any legitimate public purpose. The trial court instructed the jury to decide whether the regulatory actions substantially advanced a legitimate objective. The jury returned a verdict for the developer, and the court entered judgment on that finding rather than directing a contrary result as a matter of law.
City of Monterrey v. Del Monte Dunes at Monterrey, Ltd.526 U.S. 687, 734 (1999)
The respondent Del Monte Dunes and its predecessor in interest owned a 37.6-acre ocean-front parcel in the city of Monterey that had previously served as an oil-company terminal and tank farm. The parcel contained remnants of industrial use, including tank pads, broken concrete, oil-soaked sand, and nonnative ice plant that had spread across roughly 25 percent of the site and threatened the remaining native buckwheat habitat of the endangered Smith's Blue Butterfly. The property was zoned for multi-family residential development under the city's general zoning ordinance.
Between 1981 and 1986 the landowners submitted a series of development proposals that began with 344 units and were successively reduced, at the city's suggestion, to 264 units, then 224 units, and finally 190 units. The planning commission denied each application. The city council twice overruled the commission and granted a conditional-use permit for 190 units subject to specific conditions.
After the landowners revised their plans to satisfy those conditions, devoting substantial acreage to public open space, beach access, view corridors, and buckwheat restoration, the planning commission rejected the final proposal in January 1986 and the city council denied it in June 1986 without specifying further measures the landowners could take. After five years, five formal decisions, and nineteen site plans, Del Monte Dunes filed suit in the United States District Court for the Northern District of California under 42 U.S.C. § 1983, alleging that the city's actions effected a regulatory taking, violated due process, and denied equal protection.
The district court initially dismissed the claims as unripe. The Ninth Circuit reversed and remanded. On remand the district court submitted the takings and equal-protection claims to a jury while reserving the substantive-due-process claim for the court. At trial the jury heard evidence of the city's shifting demands, inconsistent positions, and interest in acquiring the parcel for public use. The court instructed the jury that it should find for Del Monte Dunes if the city's denial either left the property without any economically viable use or failed to substantially advance a legitimate public purpose. The jury returned a general verdict for Del Monte Dunes on the takings claim, a separate verdict on the equal-protection claim, and an award of $1.45 million in damages. The district court denied the city's post-verdict motions, and the Ninth Circuit affirmed.
The Supreme Court granted certiorari to address whether liability issues on the regulatory-takings claim were properly submitted to the jury. The Court also addressed whether the court of appeals had applied an erroneous standard permitting reweighing of the city's land-use decision. Finally, the Court considered whether the rough-proportionality test of Dolan v. City of Tigard applied to this denial of development.
5 common questions
Students Frequently Ask...
When may a party move for judgment as a matter of law under Rule 50?
A party may move at any time before the case is submitted to the jury. The motion must specify the judgment sought and the law and facts that entitle the movant to relief. The court may grant the motion only after the opposing party has been fully heard on the issue.
Supporting sources
What standard governs whether the court should grant a Rule 50 motion?
The court grants the motion when the record supplies no legally sufficient evidentiary basis for a reasonable jury to find for the nonmovant on the claim or defense. The court views the evidence in the light most favorable to the nonmovant and draws all reasonable inferences in that party's favor. Credibility determinations and weighing of evidence remain for the jury.
Supporting sources
What happens if the court denies a timely Rule 50(a) motion and the jury returns a verdict?
The court is deemed to have submitted the action to the jury. The movant may renew the motion under Rule 50(b) after the verdict. Failure to file a renewed motion bars the party from challenging the sufficiency of the evidence on appeal.
Supporting sources
How does Rule 50 differ from summary judgment under Rule 56?
Rule 50 applies after a party has been fully heard at trial and tests whether the evidence is legally sufficient for a jury. Rule 56 applies before trial and tests whether the record shows no genuine dispute of material fact. Both standards ultimately ask whether a reasonable jury could find for the nonmovant.
Supporting sources
May a court grant judgment as a matter of law by reweighing witness credibility?
No. The court may not substitute its own credibility assessments or weigh conflicting testimony. Once a jury has returned a verdict supported by legally sufficient evidence, the judge may set it aside only through the mechanisms permitted by Rule 50 or by ordering a new trial.
Supporting sources
for
judgment as a matter of law
, see 9A C. Wright & A. Miller, Federal Practice and Procedure § 2522, pp. 244-246 (2d ed. 1995). See also Parklane Hosiery Co. v. Shore , 439 U. S. 322, 335-337 (1979) (issue preclusion…
is proper, a court ordinarily must look at the record in the light most favorable to the party opposing the
motion
, drawing all inferences most…
motion
for summary…
. The Court of Appeals affirmed. 95 F. 3d 1422 (CA9 1996). The court first ruled that the District Court did not err in allowing Del Monte Dunes' regulatory takings claim to be tried to a…