Daily Delay Charge Exceeds Anticipated Loss
Horizon Land hired Vertex Land to build a condo tower. The contract set a $50,000 daily penalty for late completion. Horizon anticipated only $8,000 per day in lost rent. When Vertex finished thirty days late, Horizon sought the full stipulated sum. The court refused enforcement because the amount bore no reasonable relation to the anticipated loss.