Contract Allocation of Risk
Equitable conversion (including risk of loss)
Contract Allocation of Risk
Every risk-of-loss rule in the preceding sections is a default, and a default governs only when the parties have not written a rule of their own. Equitable conversion decides who bears damage to the property between signing and closing: the majority rule passes the risk to the buyer at contract formation, while the minority rule or a statute may leave it on the seller until the deed is delivered.1 Whichever rule a jurisdiction follows, the parties remain free to allocate the risk of loss in their contract.2 An express clause therefore supersedes the conversion doctrine, which is merely a default rule.3
The majority default makes sense once you see the theory beneath it. In most American jurisdictions, a contract that equity would specifically enforce converts the buyer's interest into real estate and the seller's into personal property.4 The theory holds that equity regards as done what ought to be done, namely conveyance of the title to the buyer and payment of the price to the seller.5 Under the majority rule, that result carries the risk with it. Once the contract exists, later destruction by fire, flood, hurricane, earthquake, or other disaster is irrelevant to the parties' obligations, because the seller has kept only the right to receive the price.6
One fire, with and without a clause, shows how much a single sentence in the contract can change.
Clauses like the second one are common. They typically provide that the risk of loss remains with the seller until escrow closes, which is why equitable conversion is comparatively rare as a gap-filling rule.8 It still decides cases where the contract is silent, as Barb and Sam's first version was, and there it assigns the loss to the buyer whether or not that matches what the parties intended.9
Courts have also often mitigated the doctrine, but only partly.10 When enforcement would be unduly harsh and oppressive to a party, a court may refuse specific performance. Refusing specific performance is not the same as rescission, however, and the parties could have contracted in reference to the event themselves.11 A court's discretion after the loss cannot substitute for a term that decides the question beforehand.
A buyer who signs a silent contract in a majority-rule state carries the whole loss between signing and closing. The buyer can respond by buying casualty insurance effective from the contract date.12 Agreement is the better protection, because default law varies. Many states depart from the majority rule and place the risk on the seller, and the variation reaches other sale questions too: some jurisdictions, for example, excuse sellers by statute from disclosing psychological or stigma conditions.13 Because the default may or may not reflect what the parties intend, buyer and seller should agree on who bears the risk before closing and write that agreement into the contract, whatever the state's default.14
Item 3 shows how a clause that answers one question can leave another open. Suppose a contract for a restaurant building keeps the risk on the seller until closing and lets the buyer terminate if the building is destroyed or materially damaged. A fire does $60,000 of damage to the kitchen, the buyer still wants the building, and the buyer asks to close at a price reduced by $60,000. The buyer argues that putting the risk on the seller means the seller bears the cost of the damage. The seller answers that the clause gives a right to terminate and nothing more. Each reading has a foothold in the text. One added sentence, entitling the buyer to close with a credit for repair costs or insurance proceeds, would have ended the argument, and the drafter's silence left it to a court.
Item 2 matters because conversion reaches beyond physical destruction. Courts have extended the doctrine to post-contract zoning amendments, eminent domain proceedings, and similar developments affecting the legal status of the property.19 A clause that names only fire may therefore leave rezoning and condemnation to the default, which in a majority jurisdiction means the buyer. Lists invite exactly this gap. In a related setting, a contract that listed specific easements and accidentally omitted one would have left title unmarketable, while a contract that instead conveyed subject to all encumbrances presented a different question.20 A clause built on the general phrase risk of loss, rather than a list of perils, is less likely to leave such a gap.