Waiver of Time Requirements
Time for performance
Waiver of Time Requirements
A late party's best escape from a time-is-of-the-essence clause is the other side's willingness to give up the deadline. Once time is essential, timely tender is a condition, and a party who is late cannot enforce the contract, in law or in equity, unless the other party is willing to waive the right to timely performance.1 Waiver is also why such a clause is weaker than its text suggests. The right to insist on the date belongs to the party the clause protects, and that party can surrender it by what it says or does, sometimes without meaning to.
Waiver is not the only softener. Among the Restatement (Second) of Contracts' factors for judging a failure to perform are the extent to which the late party will suffer forfeiture and the extent to which its behavior comports with good faith and fair dealing; the next section takes those up.2 This section asks two narrower questions. What counts as a waiver? And can the party who waived take it back?
Finding Waiver
Even when a contract makes time of the essence, the parties may waive that provision.3 Waiver here is the protected party's voluntary giving up of its right to insist on the stated date. A court decides the question from what that party said and did and from what the other side was reasonably led to believe, so a party can waive without ever deciding to surrender anything.4
Reliance and forfeiture drive the doctrine. A late party who is told, or reasonably led to think, that the date is flexible has no reason to hurry, and spends the extra days arranging financing or clearing a title problem. If the protected party could then invoke the deadline and cancel, the late party would lose the contract, and perhaps a deposit, because of a delay the other side invited. Courts are not uniform on strict deadlines. Some refuse specific performance to a buyer who was only thirty minutes late, while others are more lenient, particularly toward a purchaser who stands to forfeit a large earnest money deposit.5 A court that wants to excuse a failed condition can often do so by finding that the other party waived it by conduct.6
Waiver by the protected party shows up in four recurring forms, each resting on the idea that the party behaved as though the date no longer controlled:7
- Written or oral statements, such as a promise to adjourn the closing or an assurance that the late party may take more time.
- Conduct, such as continuing to deal with the other side as though the contract is still in force after the date has passed.
- Silence or a failure to demand strict performance, when the other side is under the reasonable impression that timely performance will not be insisted on.
- Acceptance without objection of late performance of some of the other side's obligations, which can waive lateness as to the rest.
A contract for the sale of land must be in writing, so an oral promise to adjourn the closing may seem to count for nothing. It does count. The statute of frauds is typically held to be no barrier to waivers of time requirements, because a waiver gives up a right to insist on the date and does not transfer an interest in land.8
Conduct can waive as effectively as words. Parties who keep dealing after the date has passed as though the contract remains alive, by trading drafts of closing documents, discussing the buyer's financing, or scheduling a new meeting, are treated as having abandoned the deadline.9 Landlord-tenant law follows the same logic. A landlord who knows of a tenant's breach and then accepts rent for a later period may not terminate based on that breach.10 In both settings the protected party holds a power to end the relationship, and acting as though the relationship is alive is inconsistent with keeping that power in reserve.
Silence is the least obvious route, and it turns on the other side's reasonable impression. Failing to demand strict performance may be construed as a waiver, particularly where the opposing party is under the reasonable impression that timely performance will not be insisted on.11 The question is what the silence communicated, so a party's quiet is read against everything else the other side knew.
The fourth route, partial acceptance, applies where the contract imposes several performances with their own dates. Accepting without objection the late performance of some of the other party's obligations may be taken to waive late performance of the remainder.12 A seller who takes a late additional deposit and a late loan application without protest has signaled that lateness is tolerable in this deal, and the buyer may rely on that signal when the closing date arrives.
Waiving the deadline does not by itself waive every remedy. A party who elects to continue the contract after a late performance may still sue for the harm the delay caused. In a building contract that makes time essential, failure to finish by January 1 is both a failure of an express condition and a total breach. If the owner lets the contractor continue and the work is finished within a reasonable time after that election, the owner must pay the price but may still recover damages for the late completion.13 A late land closing follows the same pattern: the party who goes forward gives up the power to cancel for lateness and keeps the claim for compensation, unless that party's language or conduct also signals a renunciation of damages.14 A party who proceeds while keeping the claim should say so when electing to continue, since conduct alone can be read as giving it up.
Drafters try to head off findings of waiver, with mixed success. A determined court can often find some way to excuse a failed condition, whether by finding waiver by conduct, unconscionability, or forfeiture, and it can do so in a ruling so fact-based that it is largely immune on appeal.15 The drafter's best protection is to write the consequences of failure into the condition itself instead of leaving them to the default and remedy provisions, to document in boilerplate that all terms are to be strictly construed, to state why the condition was included, and to state that it was a fundamental inducement for one or more parties to enter the transaction.16 Those steps give the protected party a real argument, but they cannot guarantee that a court will disregard conduct that plainly treated the contract as alive.
Reinstating the Deadline
A waiver does not end the matter, because the waiving party can restore the deadline. After a waiver, the waiving party can reinstate the essentiality of time only by notifying the other party of the intention to do so and stating a reasonable time for the other party to come into compliance.18 Courts find waiver readily, in words, in continued dealing, in silence, and in the acceptance of other late performance. A party who discovered it had waived would otherwise have no way back to the clause it bargained for. Reinstatement supplies that way back, at a price: the party must say what it intends, and it must give the other side time.
The notice requirement protects the party who relaxed on the strength of the waiver. That party may have rearranged its affairs around a slower schedule, and a notice that leaves a reasonable interval gives it a fair chance to perform before the strict standard returns.
The mechanism mirrors the way time becomes essential in the first place. If the contract does not say that time is of the essence, either party may give notice setting a time for performance, provided the interval allowed is reasonably sufficient to enable the other party to perform.19 After a waiver the same device works. The notice fixes a new date and states that strict compliance will be required on it. How much time is reasonable depends on what the other party must do to perform, so a party who relied on the waiver by arranging financing on a slower timetable may need more of it.
Two misreadings are common. One treats a waiver as permanent, so that the deadline never returns. The other treats withdrawal as automatic, so that the waiving party can simply announce that the date is back. Neither is right. The deadline returns only through notice that states the intention to require timely performance and allows a reasonable time to comply.