Concept
Limits on Vesting
Vested rights
Limits on Vesting
A landowner acquires a vested right when, in good-faith reliance on a permit or on existing zoning, the owner makes substantial expenditures or otherwise changes position so that taking the right away would be inequitable. The doctrine keeps a municipality from using a rezoning or a permit revocation to defeat expectations the owner formed reasonably under the prior law.1 Where it applies, the doctrine sharply limits the zoning power. A regulation cannot eliminate a pre-existing use, because that would confiscate a vested right, and a Michigan appellate court invalidated a scheme that protected nonconforming uses only if they did not significantly interfere with the community’s master plan.2
The earlier sections built the owner’s side of the claim: the permit, the spending, the work on the ground, and what the owner knew when the money went out. A claim complete on those terms can still fail. The rule ends in a judgment about inequity, and that judgment takes in the government’s conduct and the soundness of the permit. Three limits follow. A change in the law may already be under way when the developer applies. A municipality may act in bad faith, either by changing its law to stop one project or by stalling an application. And the permit itself may be one the government should never have issued.
These limits apply even in states that vest rights at the filing of an application, so an owner who cleared the earlier screen can still lose here. They also differ from amortization. Amortization asks how long a nonconforming use may continue, not whether a right vests in the first place. In the two dozen or so jurisdictions that approve it, courts claim to require a reasonable period for the particular use but in practice defer to rough-and-ready lines, and one can find cases upholding and cases invalidating periods from 1 to 30 or more years.3
Pending Ordinances and Moratoria
The vested rights rule protects reliance on existing zoning, and the word loses force once the government has begun to change the law. The pending ordinance doctrine states the consequence: if a change in the law is pending when a developer applies for a permit, no rights may vest.4 In a majority-rule state the result follows automatically, because the date of application is not a vesting event there, and the owner must still hold a permit and spend substantial sums before the law changes.
The doctrine does its real work in states that vest rights at application. A significant and growing number of jurisdictions fix the governing law as of the permit application and do not require a showing of expenditures in reliance on a permit.5 Utah qualifies the approach. In Western Land Equities, Inc. v. City of Logan, the court held that an applicant for a building permit is vested as of that date “unless there are pending changes in zoning ordinances which would prohibit the use applied for, or unless the municipality or county could show a compelling, countervailing reason for exercising its police power retroactively to the date of application.”6
The exception fits the logic of early vesting. Once expenditures drop out of the test, the owner’s changed position can no longer justify protection, and an applicant who files after a prohibiting change is already pending has relied on nothing the government had not already put in doubt. If a filing alone could capture the old law at that point, every announcement of a new plan would set off a race to the permit counter, because publicity about a coming plan can prompt developers to build, or at least to vest a right to build, before stricter controls arrive.7 Coupled with the power to divest rights because of serious public health or safety concerns, the pending ordinance rule is a compromise between fairness to developers and the need to protect the public interest.8
The filing must also be a proper one. In one case a builder emailed the zoning office that it intended to excavate a drainage ditch and harvest trees on its property. The city later enjoined the work because no permit had been properly applied for, and the owner argued that the date of the injunction was its date of vesting. The court flatly rejected the argument: without a proper application, it would be difficult to say with certainty what rights had vested, or when.9
Courts that let a newly enacted or pending ordinance defeat an application divide over how much the city must show. Some uphold the denial when convinced that the city acted to further the general welfare and did not arbitrarily single out the applicant. Others uphold it only if the new ordinance was pending when the permit was denied. In some jurisdictions the technique does not work at all.10 A Massachusetts court in National Amusements v. Commissioner of Inspectional Services Department held that a zoning amendment may supersede a permit application and so frustrate it. The Colorado court in City of Aspen v. Marshall held that a municipality may refuse a permit for a use repugnant to a pending ordinance, even though the use conformed to the regulations in force when the owner applied.11
The two applicants differ in one fact: where the government’s announcement fell in relation to the filing. The doctrine looks at the state of the lawmaking process on the filing date, and the pending change must be one that would prohibit the use applied for.12 A proposal that surfaces only after a complete application is filed leaves the filing intact in a state that vests at application.
A municipality that wants to avoid this race has a better tool than hasty legislation. The proper course is to pass an interim ordinance freezing development before the race begins.13 Without a freeze, developers could defeat the plan with inconsistent vested uses before the plan exists. Cities use interim zoning or moratoria to hold development in place while they adopt comprehensive plans, zoning ordinances, or growth management programs, to gain time to solve problems of overburdened schools, water, or sewer service, and to head off a proliferation of uses such as adult entertainment, fast food restaurants, or cellular towers.14
A freeze works only if it takes effect before developers can react, so it is usually enacted without the notice and hearing that accompany ordinary land use controls. That is why it is controversial.15 The Supreme Court has upheld the facial validity of moratoria that deny all use or value of land against takings challenges, though an unreasonable moratorium may be found to be a taking as applied. In some jurisdictions, authority to impose a freeze or moratorium may be questionable.16
The best summary of the requirements for a valid moratorium comes from the Minnesota Supreme Court’s 1976 decision in Almquist v. Town of Marshan, which held that a moratorium on building permits is valid if:17
- The local government adopted it in good faith.
- It is not discriminatory.
- It is of limited duration.
- It serves the purpose of developing a comprehensive zoning plan.
- The local government acts promptly to adopt that plan.
Each condition guards against a freeze becoming a device for stopping one owner or postponing decisions indefinitely. Action not supported by a planning process is ill-advised and, in a jurisdiction with a meaningful consistency requirement, may be invalid.18
A city that cannot formally impose a freeze may still slow the application. Administrative action that delays approval while new studies are completed and the new law is enacted is likely to prevent vesting in most states, provided the action is not deceptive. A permit willfully withheld through deceptive conduct leaves the intervening law inapplicable to the applicant, and an action for damages may lie.19
The developer who files first therefore does not always win the race, and neither does the city that enacts first. A developer loses if a change was already pending on the filing date. A city loses if it reached its new law by stalling an application through deception. A city that adopts a good-faith interim ordinance before the race begins ends the contest before it starts, which is why a freeze, and not hurried legislation or quiet delay, is the municipality’s proper tool.
Municipal Bad Faith
Municipalities, like developers, must act in good faith. Courts that otherwise follow the majority late-vesting rule make an exception when a municipality changes its law primarily to thwart a particular development without clear justification.21 The exception has two parts: the city’s purpose was to stop this project, and nothing clearly justifies the change apart from that purpose.
The limit is needed because the majority test gives the municipality control over timing. An owner vests only by holding a permit and spending substantial sums before the law changes, and the city decides both when the permit issues and when the new ordinance takes effect. Without a good-faith requirement, a city could sit on a complete application until an ordinance passed, or aim a law at one project just before approval, and the owner’s diligence would count for nothing. The conditions for a valid moratorium make the same demand, since a freeze must be adopted in good faith.22
Most governmental bad faith arises in the permitting process itself, where authorities drag their feet, mislead the applicant, or otherwise hinder the application. A permit willfully withheld by deceptive conduct leaves the intervening law inapplicable to the applicant and may support an action for damages.23 Unreasonable delay in issuing a permit may likewise bar a municipality from applying a newly enacted law.24 The line between these cases and the lawful delay described above is candor. A city that holds an application openly while it completes studies and enacts a new law generally prevents vesting, and deception is what removes that protection.
A rezoning that follows closely on a permit application is not bad faith in every case. If a court finds that protection of the general welfare motivated the new law, the court applies it even where permit issuance triggered its passage.25 Some courts likewise uphold a denial under a new law when convinced that the city acted to further the general welfare and did not arbitrarily single out the applicant.26 A proposal is often how a community learns that its zoning allows something it cannot tolerate, so a rule treating every later law as suspect would let any applicant disable the zoning power by filing at the right moment. The inquiry turns on why the municipality acted, and timing is only evidence of that purpose.
The municipality sometimes causes the missing element in the owner’s record. In one case, a landowner postponed an application for a land use permit at the request of city legislators who were at that moment quietly preparing to rezone the area. The court held it inequitable to let the municipality deny the use to which the landowner could have obtained a vested right before the rezoning, had the owner not accommodated the very legislators who then rezoned.27 Under the majority test the owner’s lack of a permit would ordinarily defeat the claim, yet the gap was the government’s doing. Estoppel against a municipality is rarely applied, but it remains available to a person victimized by inequitable application of the police power, and the next section takes it up.
Illegally Issued Permits
The earlier sections assumed that the permit the owner relied on was a proper one. Some jurisdictions require a valid permit before rights can vest,29 and the general proposition is that no rights vest under a permit issued illegally or by mistake.30 The rule applies even when the error belongs entirely to the government. An owner can hold a permit, spend heavily, and honestly believe the project lawful, and still lose, because the question is whether the permit could reasonably be relied on, not how much the owner spent.
Two reasons support the rule. First, official error should not repeal an enacted law. If an inspector could waive a height limit by overlooking it, the limit would bind only the owners whose applications were reviewed correctly. Second, everyone is presumed to know the extent of local officials’ power, and an applicant must use reasonable diligence to learn whether the authorized action is legal.31 That duty puts the risk of an obvious mistake on the party best placed to catch it, who can read the ordinance and the map before spending anything. Estoppel rarely rescues the owner, because estoppel against a municipality is rarely applied.32
Parkview Associates v. City of New York shows how far the rule reaches. A city building official misread the zoning map and issued a permit for a building taller than the district’s height limit allowed, and the builder completed it. Neighbors raised the alarm, and the city revoked the permit as to the portion that violated the limit. The New York Court of Appeals refused to estop the city. It reasoned that the policy reasons against estopping a governmental entity foreclose it in all but the rarest cases, and that a good-faith inquirer exercising reasonable diligence would readily have found the limit and the bureaucratic error. The builder had to remove the offending stories.33
Parkview shows what the diligence duty does to the ordinary reliance analysis. The builder had finished a building, a far larger commitment than most owners who win vesting cases ever show, and the commitment counted for nothing because a good-faith inquirer could have found the limit in the public record. The size of the loss measures only what the owner stands to lose when the reliance was unreasonable.
The rule is not ironclad. Some courts apply an “honest error” doctrine that bars revocation of a permit when an official made a good-faith mistake within the apparent scope of the official’s authority, and exceptional circumstances can justify relief. Numerous cases have found rights vested under an illegal permit or estopped the municipality.34
A permit that rests on an ambiguous ordinance falls on the favorable side of the line. In Crow v. Board of Adjustment of Iowa City, an inspector issued a permit for a veterinary hospital in a district that permitted hospitals, and the city attorney supported that reading. The owner demolished a house, excavated, and signed contracts. The ordinance was ambiguous about whether hospitals included veterinary hospitals, and the permit conferred a vested right.35 The difference from Parkview lies in the defect. An unequivocal height limit leaves no second reading, so diligence would have exposed the error. An unclear use category leaves room for the official’s reading to be a defensible interpretation, and the owner’s demolition, excavation, and contracts then count as ordinary project-specific commitments.
An owner who cannot establish a vested right in an improperly issued permit may still have a tort action for damages for the loss the permit caused.36 The route is narrow. Municipalities are generally immune from tort liability for governmental or discretionary acts, with exceptions. In a number of states the public duty doctrine also bars negligence liability, on the theory that a municipality exercising its police power acts for the general public and owes no duty to any particular person. Courts are also reluctant to make a city compensate every builder who relied on an erroneous permit, because that would expose local authorities to virtually unlimited liability.37 An owner who cannot establish vesting, honest error, or estoppel therefore often bears the loss.